When a contract does not generate work orders, the cause is usually in the contract setup.
Start with the timing and status first.
Check these points first
Review these common causes:
the contract has not reached its start date yet
the contract has passed its end date
the contract was terminated
the recurring schedule does not produce the expected next date
Days in advance is later than expected
the contract type uses different logic than expected
object-related setup affects how generation is created